MastenPark

Projects.MastenPark History

Hide minor edits - Show changes to output

Changed line 1 from:
Wireless Network for Northampton
to:
Wireless Network for Masten Park
Changed line 4 from:
To deploy a wireless network, providing internet access to all clients in the mapped area surrounding The Foundry
to:
To deploy a wireless network, providing access to the BuffaloMesh.net wireless network for all clients.
Deleted line 21:
|| || || || ||
Changed line 22 from:
||NOne||$0.00||$0.00|| ||
to:
|| || || || ||
Added lines 1-25:
Wireless Network for Northampton
(:toc-float:)
!Charter
To deploy a wireless network, providing internet access to all clients in the mapped area surrounding The Foundry
!Required resources
* Minimum of 2 persons
* Ladder
* Power drill
* Wire cutters
* 2 pairs of work gloves
* Laptop or tablet
* 1 3 ft. patch cable


! Projected Timeline
If only 2 persons are working, 3 nodes per day can feasibly be deployed.  Assuming one work party day per week, and 1 weeks per month, then this project should be complete by 1.5 months.

!Budget

||border=1
||!Item||!Price per unit||!Line Total||!Item Link||
||NOne||$0.00||$0.00|| ||
||Slack Cost (Misc hardware)||$600.00||$600.00||This is miscellania, such as concrete anchors, wire ties, etc etc.||
|| || || || ||
||Total|| ||$600.00|| ||
Page last modified on January 19, 2015, at 03:48 PM