MastenPark

Wireless Network for Masten Park

On this page... (hide)

  1.   1.  Charter
  2.   2.  Required resources
  3.   3.  Projected Timeline
  4.   4.  Budget

1.  Charter

To deploy a wireless network, providing access to the BuffaloMesh.net wireless network for all clients.

2.  Required resources

  • Minimum of 2 persons
  • Ladder
  • Power drill
  • Wire cutters
  • 2 pairs of work gloves
  • Laptop or tablet
  • 1 3 ft. patch cable

3.  Projected Timeline

If only 2 persons are working, 3 nodes per day can feasibly be deployed. Assuming one work party day per week, and 1 weeks per month, then this project should be complete by 1.5 months.

4.  Budget

ItemPrice per unitLine TotalItem Link
Slack Cost (Misc hardware)$600.00$600.00This is miscellania, such as concrete anchors, wire ties, etc etc.
    
Total $600.00 